How to Prepare Your Home for a Remodel

  • By Nate Zaharia, owner of Trevix Builders
  • Updated November 27, 2026

Short answer: clear the room and the path to it, make every material decision before the first day, set up a temporary kitchen or plan which bathroom you will use, and agree with your contractor on access, working hours and how you will communicate. An hour of preparation saves days during the job.

One to two weeks before: decide everything

  • Finalize materials. Tile, vanity or cabinets, counters, fixtures, glass, paint colors and hardware. Decisions made mid-project cost time.
  • Confirm what has arrived. Ask which materials are on hand and which are still on order.
  • Read the scope once more. Check that the written proposal matches what you expect, room by room.
  • Ask about permits. Your proposal should say who is responsible. See our permit guide.

The week before: clear the space

  • Empty the room completely: cabinets, drawers, counters, shelves and walls.
  • Clear the path from the front door to the room. Move rugs, shoes, plants and small furniture.
  • Take pictures and mirrors off shared walls in the next room. Demolition can shake them loose.
  • Decide where materials and tools can be kept, such as part of the garage.
  • Make space in the driveway or at the curb for the crew.

Plan how you will live

For a bathroom remodel

The bathroom is out of service for the whole job. Our recent bathrooms took about 2–3 weeks of construction. If it is your only bathroom, raise that at the consultation so the schedule can account for it.

For a kitchen remodel

Set up a temporary kitchen in another room with a microwave, a toaster oven, a coffee maker and the fridge if it can be moved. Plan where you will wash dishes. Our recent kitchens took about three weeks. See what to expect week by week.

Agree on the practical details

  • Access: how the crew gets in if you are not home.
  • Hours: when work starts and ends each day.
  • Pets and children: where they will be during working hours. Doors are open and tools are out.
  • Alarm and wifi: anything the crew needs to know.
  • Who to call: one person for questions, and how they prefer to hear from you.

What should your contractor do to protect your home?

Floors should be covered and taped before demolition starts, and the site should be cleaned at the end of each day. In our Escondido project, the photos show the floor protection in place before the wall was opened. A clean site at the end of each day is one of the things we insist on at every job.

What should you expect on the first day?

  • Protection goes down first, then demolition begins.
  • It is the loudest and dustiest day of the job.
  • Hidden problems, such as an old leak, show up now. You should hear about them right away, with the cost in writing before anything extra is done. See what a change order is.

During the job

  • Answer questions quickly. A fast answer keeps the crew moving.
  • Walk the job with your contractor regularly and raise concerns when you see them, not at the end.
  • Put any change in writing.

Next step

See how long a bathroom remodel takes, or request a free in-home consultation.

Quick answers

How do I prepare my house for a remodel?

Empty the room, clear the path from the front door, finalize every material choice before the first day, plan which bathroom or temporary kitchen you will use, and agree on access, working hours and who to call.

Can I live in my house during a bathroom or kitchen remodel?

Most homeowners do. Plan to use another bathroom during a bathroom remodel, or set up a temporary kitchen in another room during a kitchen remodel.

What happens on the first day of a remodel?

Floor protection goes down, then demolition begins. It is the loudest and dustiest day, and it is when hidden problems such as old leaks are found.