What to Expect During a Kitchen Remodel, Week by Week

  • By Nate Zaharia, owner of Trevix Builders
  • Updated November 27, 2026

Short answer: our recent kitchen remodels in Mira Mesa and Santee each took about three weeks of construction. Both kept their existing layout. Planning and ordering happen before that, and the order of work is the same on almost every kitchen: demolition, rough work, cabinets, countertops, then finishes.

This is a typical sequence for a kitchen that keeps its layout. Your proposal includes the schedule for your own project.

Before construction: what has to happen first?

  • Consultation and written estimate. We see the space, measure and talk through how you use the kitchen.
  • Selections. Cabinets, countertop material, sink, faucet, backsplash, flooring and hardware.
  • Ordering. Cabinets usually have the longest lead time, so construction is scheduled around their delivery.
  • Permit, if needed. Review time comes before construction. See our permit guide.

Having materials on hand before demolition is what keeps the construction phase short.

Week 1: demolition and rough work

  • Floors and nearby rooms are protected.
  • Old cabinets, counters, backsplash and flooring come out.
  • Hidden problems, such as old leaks or damaged drywall, show up here and are repaired.
  • Plumbing and electrical are updated where the new kitchen needs them.
  • Walls are patched and prepared.

Week 2: cabinets and countertop measuring

  • New cabinets are installed and leveled.
  • The countertop is measured from the installed cabinets. Stone and quartz tops are cut to those exact measurements, so there are a few days between measuring and installation.
  • Flooring goes in, depending on the plan for your kitchen.

This is the week the kitchen starts to look like a kitchen again, and also the one with a built-in wait while the countertop is fabricated.

Week 3: countertops and finishes

  • Countertops are installed.
  • Backsplash goes up, whether tile or a full-height slab.
  • Sink, faucet and appliances are connected.
  • Hardware, paint touch-ups and lighting are finished.
  • A final walkthrough to review the work and address remaining items.

What did this look like on real projects?

  • In Santee, the kitchen kept its layout and the homeowner's appliances. It got new dark shaker cabinets, marble-look quartz counters with a full-height backsplash, a black double-bowl sink and new flooring, in about three weeks.
  • In Mira Mesa, a U-shaped kitchen was rebuilt with white shaker cabinets to the ceiling, quartz counters, new appliances and recessed lighting, also in about three weeks.

What can add time?

  • Layout changes: moving the sink, range or a wall. See keep your layout or change it.
  • Lead times: custom cabinets or special-order materials.
  • Hidden damage: repairs found during demolition.
  • Permit review and inspections.
  • Changes mid-project: written up as change orders with price and schedule impact.

How do you live without a kitchen for three weeks?

  • Set up a temporary kitchen in another room: a microwave, a toaster oven, a coffee maker and the fridge if it can be moved.
  • Plan where you will wash dishes, such as a bathroom or laundry sink.
  • Empty the cabinets and counters before the first day.
  • Expect some noise and dust in week one. Protection goes up first, and the crew cleans as they go.

Next step

See our kitchen remodeling page or request a free in-home consultation and written estimate.

Quick answers

How long does a kitchen remodel take?

Our recent kitchen remodels in Mira Mesa and Santee each took about three weeks of construction. Both kept their existing layout. Planning and ordering come before that.

What is the order of work in a kitchen remodel?

Demolition and rough plumbing and electrical first, then cabinets, then countertop measuring and installation, then backsplash, fixtures, appliances and finishes.

Why is there a wait for countertops?

Stone and quartz countertops are measured from the installed cabinets and cut to those exact measurements, so there are a few days between measuring and installation.